How Much Deposit Can a Contractor Take in California on a Large Job?

By , Founder, NameVerse, Inc. · · · 6 min read

Worked examples in this guide are illustrative, not customer data — see our editorial standards.

You sign a $60,000 kitchen remodel. The cabinets have to be ordered this week and the supplier wants to be paid. In most states the deposit covers that. In California the most you can take at signing is $1,000. This page covers what the limit is, why there is no way around it for big jobs, and how to set up the payments so the job still pays for its own materials.

How much deposit can a contractor take in California?

On a home improvement contract, no more than $1,000 or 10 percent of the contract amount, whichever is less. The rule is in Business and Professions Code section 7159.5. The contract amount is the whole price, including labor, materials and profit, but not finance charges.

"Whichever is less" is the part people forget:

  • On a $4,000 job, the limit is $400.
  • On a $10,000 job, the limit is $1,000.
  • On a $60,000 job, the limit is still $1,000.

Above $10,000, the 10 percent never applies. Every large job has the same $1,000 limit.

Is there an exception for large jobs or special-order materials?

No. The statute does not raise the limit for job size, custom orders or long lead times. After the down payment, a contractor may not request or accept a payment that is more than the value of the work performed or the material delivered. Cabinets that are ordered but not delivered do not count yet. The same rule covers money advanced by a lender or finance company.

The CSLB's guide for contractors puts it this way: except for the down payment, it is against the law to get paid before you do the work, or for materials before they have been delivered.

Why do contractors need money up front on a large job?

Because the costs arrive weeks before the revenue. Materials are ordered before the first day on site. The crew and the subs are paid every week. Permits and dumpsters are paid at the start. On a job that runs two months, waiting for one check at the end means lending the customer the price of their own kitchen. That is a fair reason to want money early. California does not argue with the reason. It moves the money out of the deposit and into the progress payments.

How do you fund a large job when the deposit stops at $1,000?

With the payment schedule. The contract can require payments before the job is finished, as long as each one is stated in dollars and cents and names the work, services, materials or equipment it pays for. So the schedule should start early and follow the costs. Here is one way to lay out that $60,000 kitchen:

  1. Down payment at signing: $1,000.
  2. Demolition complete and framing changes done: $8,000.
  3. Cabinets and windows delivered to the site: $16,000.
  4. Rough plumbing and electrical pass inspection: $12,000.
  5. Cabinets installed and countertops set: $14,000.
  6. Final walkthrough: $9,000.

Three things make a schedule like this work:

  • Bill deliveries. Material delivered to the job counts. Schedule the delivery early and make it a payment of its own, so the cabinet money comes in when the cabinets do.
  • Keep the first phases short. A payment due when demolition is done arrives in days, not weeks.
  • Match each amount to what it pays for. A payment cannot be larger than the value of what has been done or delivered at that point. Loading the early payments beyond that breaks the same rule as an oversized deposit.

The gap that is left is the time between placing an order and its delivery. A trade account with your supplier, with the invoice due after delivery, covers that gap without the customer's money. For how to word milestones so nobody argues about them, see deposits and progress billing on bigger jobs.

What happens if a contractor takes more than the limit?

It is a crime, not a paperwork slip. Taking a down payment over the limit, or a payment ahead of the work or the delivered materials, is a misdemeanor. The penalty is a fine of $100 to $5,000, up to one year in county jail, or both. In an area under a declared state of emergency after a natural disaster, the court must impose the maximum fine. It is also cause for discipline against your license. The CSLB's contractor guide lists an excessive down payment second among the common problems it sees in home improvement contracts.

When does the $1,000 limit not apply?

  • An approved bond or joint control. A contractor who furnishes a performance and payment bond, or a joint control approved by the CSLB registrar, covering full performance and payment is exempt from the down payment and progress payment rules. The CSLB calls these blanket bonds rare and says only about two dozen companies have been approved to use them.
  • Service and repair contracts. These are stricter. On a job of $750 or less that the customer called you about, no payment is due, and none may be accepted, until the work is completed.
  • Work that is not home improvement. The rule covers repairing, remodeling, altering or adding to residential property for an owner or tenant, including pools, solar, landscaping and fences. Commercial work and building a new house are not on that list. Confirm which rules apply before you rely on that.

Do progress payments come with lien releases?

If the customer asks, yes. After any payment, and before the next one, the contractor must on request provide a full and unconditional lien release for the portion of the work that has been paid for. The customer may hold back further payments until they have it. On a job with subs and suppliers, collect those releases as you go.

Set the schedule once

Write the schedule into the contract, with the headings and statements the law requires. What a California home improvement contract must include has the full checklist. Then check it against the current rules on the CSLB site and have an attorney read it.

After that, the job is to send each payment request the day the milestone lands. Tabsy Express keeps the deposit and every milestone on the job. When the cabinets come off the truck, you send that invoice from the driveway. Your client pays in their browser from a text or email link, by card, ACH or Apple Pay. $39 a month after a 30-day free trial, and no charge until the trial ends. See Tabsy Express.

Built for contractors

Estimate, contract, invoice, paid. One system.

Tabsy runs the job from the first estimate to the last payment. Every subscription starts with a 30-day free trial, and nothing is charged until the trial ends.

Working solo

Tabsy Express

Estimates, contracts your client signs in their browser, invoices and card or ACH payments, all in one place.

$39/month after your 30-day free trial

Start free trial See Tabsy Express →

Running a crew

Tabsy LPM

Leads, estimates, contracts, projects, dispatching and billing for teams of 2 to 30, on web, iOS and Android.

From $70/month for 2 users, every feature

See Tabsy LPM Compare plans and pricing →

Quick answers from this guide

How much deposit can a contractor take in California?

On a home improvement contract, no more than $1,000 or 10 percent of the contract amount, whichever is less. The rule is in Business and Professions Code section 7159.5. The contract amount is the whole price, including labor, materials and profit, but not finance charges.

Is there an exception for large jobs or special-order materials?

No. The statute does not raise the limit for job size, custom orders or long lead times. After the down payment, a contractor may not request or accept a payment that is more than the value of the work performed or the material delivered. Cabinets that are ordered but not delivered do not count yet. The same rule covers money advanced by a lender or finance company.

Why do contractors need money up front on a large job?

Because the costs arrive weeks before the revenue. Materials are ordered before the first day on site. The crew and the subs are paid every week. Permits and dumpsters are paid at the start. On a job that runs two months, waiting for one check at the end means lending the customer the price of their own kitchen. That is a fair reason to want money early. California does not argue with the reason. It moves the money out of the deposit and into the progress payments.

How do you fund a large job when the deposit stops at $1,000?

With the payment schedule. The contract can require payments before the job is finished, as long as each one is stated in dollars and cents and names the work, services, materials or equipment it pays for. So the schedule should start early and follow the costs. Here is one way to lay out that $60,000 kitchen:

What happens if a contractor takes more than the limit?

It is a crime, not a paperwork slip. Taking a down payment over the limit, or a payment ahead of the work or the delivered materials, is a misdemeanor. The penalty is a fine of $100 to $5,000, up to one year in county jail, or both. In an area under a declared state of emergency after a natural disaster, the court must impose the maximum fine. It is also cause for discipline against your license. The CSLB's contractor guide lists an excessive down payment second among the common problems it sees in home improvement contracts.

Do progress payments come with lien releases?

If the customer asks, yes. After any payment, and before the next one, the contractor must on request provide a full and unconditional lien release for the portion of the work that has been paid for. The customer may hold back further payments until they have it. On a job with subs and suppliers, collect those releases as you go.

Free checklist

Invoice clearly, get paid faster, and chase fewer late payments — from estimate to final payment.

Get the free Get-Paid-Faster checklist
30 days free · $0 today
Every feature · Cancel anytime.
Start Free Trial